发明名称 CONSTRUCTION METHOD OF PILE FOUNDATION TYPE TANK
摘要 <P>PROBLEM TO BE SOLVED: To execute the construction works of a pile foundation type tank in parallel and to shorten a construction period compared to a conventional construction method. <P>SOLUTION: The construction method of the pile foundation type tank for constructing a foundation by placing a plurality of piles in the ground and constructing a slab, a sidewall and a roof on the foundation includes: a first process of placing initial piles in the ground positioned at least below the sidewall; a second process of constructing the roof; a third process of lifting the roof upwards and connecting the uppermost stage part of the sidewall under the roof; a fourth process of completing the sidewall by repeatedly constructing a lower stage part at the uppermost stage part and lifting it upwards; a fifth process of placing additional piles in the ground other than the part below the sidewall in parallel with the fourth process; and a sixth process of constructing the slab so as to cover the initial piles and the additional piles. <P>COPYRIGHT: (C)2012,JPO&INPIT
申请公布号 JP2012001886(A) 申请公布日期 2012.01.05
申请号 JP20100134890 申请日期 2010.06.14
申请人 IHI CORP 发明人 FUJINO TETSUJI
分类号 E04H7/18;E02D27/38 主分类号 E04H7/18
代理机构 代理人
主权项
地址
您可能感兴趣的专利