发明名称 EXECUTION METHOD OF PILE
摘要 PROBLEM TO BE SOLVED: To provide an execution method of a pile capable of increasing bearing force of the pile by making use of an expansion property by water absorption of a steel making slag occurring in a steel making process. SOLUTION: The pile 1 is erected into an excavated hole H, at the same time, the circumference section of the pile 1 and the inside section are filled with expansible slags 2, and the slags 2 are expanded to increase bearing force of the pile 1.
申请公布号 JP2003090037(A) 申请公布日期 2003.03.28
申请号 JP20010398697 申请日期 2001.12.28
申请人 NISHIWAKI JUN;GEOTOP CORP;HIROKO GIKEN KK 发明人 NISHIWAKI JUN;YABUUCHI SADAO;HIMEDA MASATAKA
分类号 E02D5/50;E02D27/14;(IPC1-7):E02D5/50 主分类号 E02D5/50