摘要 |
<P>PROBLEM TO BE SOLVED: To provide a tunnel construction method that makes constructibility proper and that dispenses with drastic extension of a construction period. <P>SOLUTION: This tunnel construction method is invented by focusing attention on the fact that bleeding water gathers onto a top 5a of a waterproof sheet 5 during placement of secondary lining concrete 6. Bag cement 10 is disposed on this location. The bag cement 10 includes a bag body 11 that is made of a material dissolving in alkaline water of pH equal to or higher than pH of cement for use in the secondary lining concrete 6, and cement 12 that is encapsulated in the bag body 11. <P>COPYRIGHT: (C)2012,JPO&INPIT |