摘要 |
PROBLEM TO BE SOLVED: To improve the execution property and prevent dew condensation on the back of a ceiling by installing a beam connected with the upper and lower end members made of wood by bolts from the flange side on and beneath an H-steel, and suspending and supporting a cornice from the beam with suspension metals. SOLUTION: A beam 1 integrally connected with the upper and lower end members 12a, 12b made of wood by bolts from the flange side on and beneath an H-steel 11 having upper and lower horizontal flanges is installed. A cornice connected to the upper face of a ceiling panel 5 is suspended and supported from the beam 1 by suspension metals 2 fixed to the beam 1 at the upper end sections and fixed to the cornice at the lower end sections. No ceiling carrying rod or no ceiling carrying rod fixing rod fixture is required, and the execution property can be improved. |